We are the main contractor for the new investment done by Dozamel Sp z o.o. located in Wrocław Industrial Park (near C3 building). Construction of the new warehouse shall be finished in November 2012. The building area is 3000 square meters. Our company is committed to the preparation and execution of the construction project and implementation of cross-industry projects.
gallery >The agreement included the assembly of about 220.0 Mg of equipment including piping (no electrical connection and no commissioning) for the construction of the mill at the plant belonging to Best Oil company in Lasocice. Including the realization of welded joints according to PN-EN ISO 15609-1 standard and execution of studies of mentioned joints according to the project requirements and the PN-B-06200 standard.
gallery >Our company took part in the construction of a new passenger terminal at the airport in Wrocław. Works were carried out in the summer of 2010 and lasted several months. We have completed nearly eighty welded main girders in the roof structure.
gallery >It was a steel structure with housing, with panels and corrugated sheets with a capacity of 4563 cubic meters. Implementation took place in 2004.
gallery >It was constructed in the room previously containing old water-steam boiler fed with coal.
The new installation consists of two straw fired boilers with capacity of 400kW each and two wood fired boilers with a capacity of 200kW. It serves both as a central heating system and water heating system.
The central heating system was tailored to fit the heating demands of school buildings after their thermal modernisation. It is equipped with an automatic weather compensation system, a new heat distribution network and thermostatic valves.
The entire project was compleated within 2 months while maintaining continuous supply of heat to the buildings.
In 2009 we took part in the assembly of the huge Christmas tree at the Wrocław market square.
gallery >Our company was responsible for the installation of steel structure supporting the LCD screen.
We have completed two similar projects involving the installation of steel constructions of buildings in Busko Zdrój and Wieluń. Both have the same surface of 3085 square meters and capacity of 19 056 cubic meters. The work took place between July and September 2009.
gallery >We were responsible for modernization of a part of building on site No.2 in Wrocławskie Zakłady Zielarskie Herbapol SA (a manufacturer of herbal products). We installed air cooling ventilation system and electrical installation supporting lighting, air conditioning and powering the production equipment. Works were carried out in spring 2010.
gallery >The project included installation of gas - steam boiler with a capacity of 50 tons of steam per hour.
gallery >Our task was the assembly of steel construction of the supermarket. Area occupied by the object was approximately 2300 square meters. Works were carried out in May 2005.
In November 2004 we have completed the assembly of steel structure of sports hall in Głuchołazy.